Stages in the Review process for the Arnside and Silverdale AONB Management Plan:
Those coloured grey have been completed.
|
|
AONB Executive Committee - 25th April 2007
AONB Executive offers to carry out the review on behalf of the
Local Authorities.
(Lancashire & Cumbria CCs, Lancaster City Council,
South Lakeland District Council)
|
|
|
AONB Executive Committee - 25th July 2007
Authority to carry out the review granted and Executive
issues the required Notice under section 90(i) of the Countryside and Rights of Way Act.
|
|
AONB Executive
establish Management Plan Review working group
|
Strategic Environmental Assessment
requirement announced and SEA work commences.
|
|
|
Re-appraise the existing Vision statements
The Overall and eight theme specific Visions assessed for continued relevance.
Two new visions are added on Marine Environment and Renewable Energy/Sustainability.
|
|
|
AONB Annual Conference - 26th October 2007
Consultation on the scope of the Review and the Draft SEA Scoping Report.
|
|
|
AONB Executive Committee - 21st November 2007
Appraise consultation outcomes. Report to stakeholders.
|
|
|
AONB Executive & Review Working Group November 2007 - January 2008
|
|
Sign off
Sign off revised Vision Statements
and prepare draft Issues revision for approval
|
and
Prepare briefing/decision paper on the Extent of the Review for AONB Executive
|
AND - Publish final SEA Scoping Report following consultation
|
|
|
AONB Executive Committee - 4th January 2008
Appraise consultation outcomes - decide on extent of review and
if amendment of the existing plan is needed. Report to stakeholders. Formally adopt the Vision Statements.
|
|
|
|
|
AONB Executive & Review Working Group January - July 2008
|
|
Write Policy Responses and amend Objectives
Identify the amendments required and re-write Management Objectives as necessary.
Policy Responses introduced into draft to facilitate completion of SEA.
|
|
|
AONB Executive Committee - 23rd July 2008
Circulate draft form of Management Objectives section of the reviewed Plan to members and
circulate the outline SEA and AA assessment reports for comment.
|
|
|
AONB Officer and SEA Consultant July - October 2008
|
|
Carry out SEA/AA Assessment of amended Objectives
Test and review the Management Plan Policy Responses and the Management Objectives
against SEA Objectives and criteria and complete Appropriate Assessment process.
|
|
Review of Management Plan - Draft Plan written
Complete a draft of the Management Plan and Environmental Report
ready to circulate to Technical Officers Group prior to Executive Meeting of 22nd October.
|
|
|
AONB Executive Committee - 22nd October 2008
Circulate draft form of Management Plan and Environmental Report to members.
Agree the distribution of the draft documents for public and formal partner consultation.
|
|
|
Carry out Consultation October - December 2008
Public and Stakeholder consultation on both Draft Environmental Report and
the draft Management Plan
(including online website consultation)
|
|
|
|
|
AONB Executive & Review Working Group December 2008 - January 2009
|
|
Appraise Stakeholders of the outcome of the Public and Partner Consultation
Report to stakeholders
|
Discussion with Natural England following formal comment
Make any necessary amendments to the documents following NE comment
|
|
|
AONB Executive & Review Working Group January - February 2009
|
|
Develop Action Plan Document
Review and develop detail AONB Action Plan to accompany the 2009 - 14 Management Plan.
Carry out Public and Stakeholder consultation on the draft Action Plan
(including online website consultation) 4th Feb - 20th March 2009
|
|
|
AONB Executive Meeting - 4th February 2009
|
|
Sign off of Management Plan by Executive Committee
Documents forwarded to Local Authorities for Adoption
|
Strategic Environmental Assessment
Statement of how Environmental Report findings have influenced Plan Review
|
|
|
Final Overview of Plan by Natural England - April - May 2009
Notification received that the Plan documents meet the legislative requirements for AONB Management Plans.
|
|
|
Adoption of Plan by Local Authorities - May & June 2009
Confirmation received that the Plan documents were adopted by all local authority partners.
|
|
|
New AONB Management Plan published - June 2009
Public launch event held June 17th at the AONB Annual Conference
|
|
|
Review Reports & Summary of the new Plan Published - July 2009
Documents submitted to the Secretary of State once final Action Plan agreed.
|
|
|
Implementation of Plan - July 2009 - June 2014
Monitor and report on progress with AONB Action Plan.
|
|
|
|