Stages in the Review process for the Arnside and Silverdale AONB Management Plan:
Those coloured grey have been completed.
|
|
AONB Executive Committee - 25th April 2007
AONB Executive offers to carry out the review on behalf of the
Local Authorities.
(Lancashire & Cumbria CCs, Lancaster City Council,
South Lakeland District Council)
|
|
|
AONB Executive Committee - 25th July 2007
Authority to carry out the review granted and Executive
issues the required Notice under section 90(i) of the Countryside and Rights of Way Act.
|
|
AONB Executive
establish Management Plan Review working group
|
Strategic Environmental Assessment
requirement announced and SEA work commences.
|
|
|
Re-appraise the existing Vision statements
The Overall and eight theme specific Visions assessed for continued relevance.
Two new visions are added on Marine Environment and Sustainability.
|
|
|
AONB Annual Conference - 26th October 2007
Consultation on the scope of the Review and the Draft SEA Scoping Report.
|
|
|
AONB Executive Committee - 21st November 2007
Appraise consultation outcomes. Report to stakeholders.
|
|
|
AONB Executive & Review Working Group November 2007 - January 2008
|
|
Sign off
Sign off revised Vision Statements
and prepare draft Issues revision for approval
|
and
Prepare briefing/decision paper on the Extent of the Review for AONB Executive
|
AND - Publish final SEA Scoping Report following consultation
|
|
|
AONB Executive Committee - 23rd January 2008
Appraise consultation outcomes - decide on extent of review and
if amendment of the existing plan is needed. Report to stakeholders.
|
|
|
|
|
AONB Executive & Review Working Group January - March 2008
|
|
Write/amend Objectives and prepare draft Action Plan
Identify the amendments required and re-write Objectives,
draft the review report and commence revision of the Action Plan
|
AND - Prepare SEA Environmental Report
Test and review the Management Plan Objectives and the draft Action Plan
against SEA Objectives and criteria
|
|
|
AONB Executive Committee - 23rd April 2008
Review amendments and other outcomes - sign off draft review report and
draft environmental report. Report to stakeholders.
|
|
|
Carry out Consultation April - June 2008
Public and Stakeholder consultation on both Draft Environmental Report and
the draft Review Report revised Action Plan or draft new Management Plan
(including website consultation - Management Plan Review Online)
|
|
|
|
|
AONB Executive & Review Working Group July - September 2008
|
|
Appraise consultation outcomes
Make any necessary amendments to the documents. Report to stakeholders
|
Documents to Natural England
for formal comment
|
|
|
AONB Executive & Review Working Group October - November 2008
|
|
Appraise Local Authorities of Natural England consultation outcomes
Report to stakeholders
|
Discussion with Natural England following formal comment
Make any necessary amendments to the documents following NE comment
|
|
|
AONB Executive & Review Working Group December 08 / January 09
|
|
Documents forwarded to Local Authorities for Adoption
|
Strategic Environmental Assessment
Statement of how Environmental Report findings have influenced Plan Review
|
|
|
Review Report & amended/new Plan Published - March 2009
Documents submitted to the Secretary of State.
|
|
|
|